The City of Inver Grove Heights is planning for the Dawn Way Street Rehabilitation project for 2023.
Tentative Project Timeline
- Improvement Hearing, Order Plans, and Specifications (City Council Meeting Item): October 24, 2022
- Approve Plans and Specifications, Authorize Bidding (City Council Meeting Item): December 12, 2022
- Project Bidding: January through February 2023
- Construction: May through October 2023
- Assessment Hearing (City Council Meeting Item): Fall 2023
Previous Meetings & Project Documents
- Public Improvement Hearing: October 24, 2022
- Information Meeting for Improvements: October 4, 2022
- Receive Feasibility Report, Call for Improvement Hearing (City Council Meeting Item): September 12, 2022
- Feasibility Report Open House: August 25, 2022
Stay Connected
Email Notifications
Sign up for the "Notify Me" subscriber list for this project to receive updates on project progress and scheduling.
Questions
Project staff appreciates your patience during the preliminary review of this project. These are large neighborhood projects with unique pavement conditions. If you have questions or concerns, please feel free to contact either the consultant Project Manager or Assistant City Engineer via the contact info below.