2025 IGH Pavement Management Initiative - 50th Street Area St (Babcock to TH 3)
Construction Update:
On Monday, crews will begin reclaiming 50th Street, and the roadway will remain in a gravel condition until paving is completed at a later date. On Thursday and Friday, the utility crew will shift their operations to 50th Street to begin storm sewer installation. One lane of traffic will remain open during this work to maintain access. However, on Friday, 50th Street is scheduled to be fully closed between the Ashley Lane intersections.
City Contact:
Please contact David Ray, Asst. City Engineer by email:dray@ighmn.gov or call 651-450-2541.
More info at: www.ighmn.gov/pavement
* * * * * * *