Construction Update: Barbara Avenue & 46th Street Area

Formatted HTML message

2025 IGH Pavement Management Initiative - Barbara Avenue & 46th Street Area 

Construction Update

This Week (10/06–10/11):

Utility crews installed services and storm sewer along August Way and Audrey Avenue north of August Way. Concrete driveways along Bacon Avenue (north of 46th Street), Upper 45th Street, and the north half of Barbara Avenue were poured.

Sanitary sewer work along Hwy 52 in the townhome area off of Barbara Avenue occurred this week. 

The road crew will also be working on raising manhole and gate valve castings in areas where the base course of asphalt pavement has already been placed, preparing these streets for the final wear course of paving.

Next Week (10/13–10/18):

Utility crews will be installing the remainder of the services and storm sewer along August Way and Audrey Avenue north of August Way. 

The road crew will also be prepping the road base for paving with potential paving to occur sometime this week. The road crew will also be working on rebuilding the road subgrade along August Way and Audrey Avenue in areas where the utility work is completed.

Please note that all work is weather-dependent and subject to change.

General Updates

Access:  

The contractor will perform work while maintaining traffic flow. However, temporary road closures may occur during utility work. Access will be restored at the end of each workday. For information regarding private driveway access, please refer to the Curb and Driveway Notice below.

Garbage Service:

As construction activities continue in your area, please be advised that garbage collection services will not be impacted. Residents should continue to place their garbage and recycling bins out on their regular collection days and in their usual locations.

Temporary Water Service

As part of the ongoing construction project, temporary water service will be provided to maintain uninterrupted water supply during water main replacement. If your property will be connected to temporary water service, you will receive advance written notice with specific details.

Please be aware of the following:

  • A temporary above-ground water line will be connected to your outside faucet or another suitable location.
  • You may notice a slight decrease in water pressure or temperature fluctuations during this time.
  • Temporary water service will remain in place until the new water main is fully installed and tested.
  • Please do not tamper with or disconnect the temporary line. If you experience any issues with your water service, contact the project representative listed in your notice.
  • The contractor may ask you to turn off your water service valve inside you home in order to connect to the temporary water service.

Temporary Mailboxes:

Due to construction in the area, temporary mailboxes will be installed to ensure uninterrupted mail delivery. Advance written notice will be provided to affected homeowners prior to the relocation of mail service. These temporary mailboxes will be located at the designated area identified in the notice provided to you and will remain in use until work is complete and normal access is restored. If you have questions about mail delivery, please contact your local post office or the project representative listed on your notice.

Curb and Driveway Notice:

The contractor will provide written notice to any homeowner whose driveway access will be temporarily impacted. If you receive a notice and need to use your vehicle during the day, you must park in the designated area indicated in the notice. Once the initial work is completed, gravel will be placed in front of affected driveways to provide temporary access until permanent repairs are made. Driveway access will be restricted again when the curb is poured and driveways are repaired. A separate advance notice will be provided before this occurs.

Right-of-Way Obstruction Notice:

Property owners are responsible for any irrigation systems, invisible dog fences, or other unpermitted obstructions located within the public right-of-way (approximately 12–15 feet behind the curb, within the boulevard area). To avoid potential damage or additional costs during construction. Please temporarily relocate your irrigation lines at least 4 feet behind the curb before work begins in your area. After topsoil is placed, you may reinstall their irrigation systems prior to sod installation. Neither the City nor the Contractor is liable for damage to any unpermitted obstructions within the right-of-way. Please turn off any irrigation zones that are near the street until work is completed.

City Contact:

Please contact David Ray, Asst. City Engineer by email or call 651-450-2541.

More info at: www.ighmn.gov/pavement

* * * * * * *

If you no longer wish to receive these messages, you may manage your preferences and unsubscribe at any time by visiting: www.ighmn.gov/list.asp?mode=del.

Please note, we will not sell or give your email address to any organization without your explicit permission.

 

Plain text message

2025 IGH Pavement Management Initiative - Barbara Avenue & 46th Street Area
Construction Update
​This Week (10/06–10/11):
Utility crews installed services and storm sewer along August Way and Audrey Avenue north of August Way. Concrete driveways along Bacon Avenue (north of 46th Street), Upper 45th Street, and the north half of Barbara Avenue were poured.

Sanitary sewer work along Hwy 52 in the townhome area off of Barbara Avenue occurred this week.

The road crew will also be working on raising manhole and gate valve castings in areas where the base course of asphalt pavement has already been placed, preparing these streets for the final wear course of paving.

Next Week (10/13–10/18):
Utility crews will be installing the remainder of the services and storm sewer along August Way and Audrey Avenue north of August Way.

The road crew will also be prepping the road base for paving with potential paving to occur sometime this week. The road crew will also be working on rebuilding the road subgrade along August Way and Audrey Avenue in areas where the utility work is completed.

Please note that all work is weather-dependent and subject to change.

General Updates
Access:
The contractor will perform work while maintaining traffic flow. However, temporary road closures may occur during utility work. Access will be restored at the end of each workday. For information regarding private driveway access, please refer to the Curb and Driveway Notice below.

Garbage Service:
As construction activities continue in your area, please be advised that garbage collection services will not be impacted. Residents should continue to place their garbage and recycling bins out on their regular collection days and in their usual locations.

Temporary Water Service
As part of the ongoing construction project, temporary water service will be provided to maintain uninterrupted water supply during water main replacement. If your property will be connected to temporary water service, you will receive advance written notice with specific details.

Please be aware of the following:

A temporary above-ground water line will be connected to your outside faucet or another suitable location.
You may notice a slight decrease in water pressure or temperature fluctuations during this time.
Temporary water service will remain in place until the new water main is fully installed and tested.
Please do not tamper with or disconnect the temporary line. If you experience any issues with your water service, contact the project representative listed in your notice.
The contractor may ask you to turn off your water service valve inside you home in order to connect to the temporary water service.
Temporary Mailboxes:
Due to construction in the area, temporary mailboxes will be installed to ensure uninterrupted mail delivery. Advance written notice will be provided to affected homeowners prior to the relocation of mail service. These temporary mailboxes will be located at the designated area identified in the notice provided to you and will remain in use until work is complete and normal access is restored. If you have questions about mail delivery, please contact your local post office or the project representative listed on your notice.

Curb and Driveway Notice:
The contractor will provide written notice to any homeowner whose driveway access will be temporarily impacted. If you receive a notice and need to use your vehicle during the day, you must park in the designated area indicated in the notice. Once the initial work is completed, gravel will be placed in front of affected driveways to provide temporary access until permanent repairs are made. Driveway access will be restricted again when the curb is poured and driveways are repaired. A separate advance notice will be provided before this occurs.

Right-of-Way Obstruction Notice:
Property owners are responsible for any irrigation systems, invisible dog fences, or other unpermitted obstructions located within the public right-of-way (approximately 12–15 feet behind the curb, within the boulevard area). To avoid potential damage or additional costs during construction. Please temporarily relocate your irrigation lines at least 4 feet behind the curb before work begins in your area. After topsoil is placed, you may reinstall their irrigation systems prior to sod installation. Neither the City nor the Contractor is liable for damage to any unpermitted obstructions within the right-of-way. Please turn off any irrigation zones that are near the street until work is completed.

City Contact:
Please contact David Ray, Asst. City Engineer by email or call 651-450-2541.

More info at: www.ighmn.gov/pavement

* * * * * * *

If you no longer wish to receive these messages, you may manage your preferences and unsubscribe at any time by visiting: www.ighmn.gov/list.asp?mode=del.

Please note, we will not sell or give your email address to any organization without your explicit permission.

SMS message

Utility crews finishing sewer/water services next week; Paving prep next week and potential paving in recently curbed area depending on conditions.