Construction Update: 50th Street Area (Babcock to TH 3)

Formatted HTML message

2025 IGH Pavement Management Initiative - 50th Street Area St (Babcock to TH 3)

Construction Update

This Week (0811-08/16):   

Utility crews completed storm sewer work along 50th Street. Concrete crews began re-pouring curb and driveways and will continue into next week. Road crews will be milling and reclaiming the east half of 50th Street on Saturday (08/16) and into next week to prepare for paving.

Next Week (08/18-08/23):   

Concrete curb and driveway work will continue. Roadway crews will be reclaiming and begin preparing the road surface for pavement.

City Contact:

Please contact David Ray, Asst. City Engineer by email or call 651-450-2541.

More info at: www.ighmn.gov/pavement

* * * * * * *

If you no longer wish to receive these messages, you may manage your preferences and unsubscribe at any time by visiting: www.ighmn.gov/list.asp?mode=del.

Please note, we will not sell or give your email address to any organization without your explicit permission.

 

Plain text message

2025 IGH Pavement Management Initiative - 50th Street Area St (Babcock to TH 3)
Construction Update

This Week (0811-08/16):  
Utility crews completed storm sewer work along 50th Street. Concrete crews began re-pouring curb and driveways and will continue into next week. Road crews will be milling and reclaiming the east half of 50th Street on Saturday (08/16) and into next week to prepare for paving.

Next Week (08/18-08/23):  
Concrete curb and driveway work will continue. Roadway crews will be reclaiming and begin preparing the road surface for pavement.

City Contact:
Please contact David Ray, Asst. City Engineer by email or call 651-450-2541.

More info at: www.ighmn.gov/pavement

* * * * * * *

If you no longer wish to receive these messages, you may manage your preferences and unsubscribe at any time by visiting: www.ighmn.gov/list.asp?mode=del.

Please note, we will not sell or give your email address to any organization without your explicit permission.

SMS message

Storm sewer done on 50th. Curb/driveway work continues. East half milling/reclaim starts 8/16, paving prep next week.