Sender Name:
City of IGH Pavement Management Initiative
Sent By:
(Automatically Sent By Website)
Send Date:
8/22/2025 4:32:07 PM
Email Subject:
Construction Update: Barbara Avenue & 46th Street Area

Formatted HTML message

2025 IGH Pavement Management Initiative - Barbara Avenue & 46th Street Area 

Construction Update

This Week: (08/18-08/23)

Utility crews continued sanitary and watermain installation along Bacon Avenue, and Upper 45th Street, towards the north half of Barbara Avenue. The sanitary has been install to Upper 45th Street and they are working their way to Barbara Avenue. The water is being installed behind them. Concrete crews began pouring curb in all areas where utility and roadway work is complete. Please be mindful of freshly poured curb and avoid driving over it.

Next Week (08/25-08/29):   

Utility crews will continue sanitary sewer installation along Upper 45th Street and down Barbara Avenue, with watermain installation following behind as a second operation. The road crew will begin tolerancing the road to get it to finish grade in preparation of paving.

Please note that all work is weather-dependent and subject to change.

City Contact:

Please contact David Ray, Asst. City Engineer by email or call 651-450-2541.

More info at: www.ighmn.gov/pavement

* * * * * * *

If you no longer wish to receive these messages, you may manage your preferences and unsubscribe at any time by visiting: www.ighmn.gov/list.asp?mode=del.

Please note, we will not sell or give your email address to any organization without your explicit permission.

 

Plain text message

2025 IGH Pavement Management Initiative - Barbara Avenue & 46th Street Area
Construction Update

This Week: (08/18-08/23)
Utility crews continued sanitary and watermain installation along Bacon Avenue, and Upper 45th Street, towards the north half of Barbara Avenue. The sanitary has been install to Upper 45th Street and they are working their way to Barbara Avenue. The water is being installed behind them. Concrete crews began pouring curb in all areas where utility and roadway work is complete. Please be mindful of freshly poured curb and avoid driving over it.

Next Week (08/25-08/29):  
Utility crews will continue sanitary sewer installation along Upper 45th Street and down Barbara Avenue, with watermain installation following behind as a second operation. The road crew will begin tolerancing the road to get it to finish grade in preparation of paving.

Please note that all work is weather-dependent and subject to change.

City Contact:
Please contact David Ray, Asst. City Engineer by email or call 651-450-2541.

More info at: www.ighmn.gov/pavement

* * * * * * *

If you no longer wish to receive these messages, you may manage your preferences and unsubscribe at any time by visiting: www.ighmn.gov/list.asp?mode=del.

Please note, we will not sell or give your email address to any organization without your explicit permission.

SMS message

PMI Update: Sanitary sewer/watermain work continues on Upper 45th, Bacon, & Barbara. Be mindful of new curb. Paving is scheduled for next week.