2025 IGH Pavement Management Initiative - 50th Street Area St (Babcock to TH 3)
Construction Update
This Week (09/15–09/20):
Utility crews have raised castings this past week while the concrete crew worked on curb along Ashley Lane. Additionally, the concrete crew worked on pouring new sidewalks along 50th Street. The road crew removed the excess road material from the road and began work to prepare the road for paving.
Next Week (09/22–09/27):
The road crew will be working to prepare the road early in the week and are planning to pave the road mid-week.
Please note that all work is weather-dependent and subject to change