2025 IGH Pavement Management Initiative - 50th Street Area St (Babcock to TH 3)
Construction Update
This Week (10/06–10/11):
Restoration work took place this week, including sod placement behind the curb. The concrete driveway aprons for the apartment building along Ashley Lane were also opened to full access.
Next Week (10/13–10/18):
Road crews will focus on completing punch list items and preparing the roadway for the final wear course paving.
Please note that all work is weather-dependent and subject to change
City Contact:
Please contact David Ray, Asst. City Engineer by email or call 651-450-2541.
More info at: www.ighmn.gov/pavement
* * * * * * *