Notify Me

  1. Sign In
  2. If you want to receive text messages enter your phone number and select Save.
  3. To subscribe or unsubscribe click Email icon and/or SMS icon next to the lists to which you wish to subscribe/unsubscribe.
Sender Name:
City of IGH Pavement Management Initiative
Sent By:
(Automatically Sent By Website)
Send Date:
10/10/2025 4:07:16 PM
Email Subject:
Construction Update: 50th Street Area (Babcock to TH 3)

Formatted HTML message

2025 IGH Pavement Management Initiative - 50th Street Area St (Babcock to TH 3)

Construction Update

This Week (10/06–10/11):

Restoration work took place this week, including sod placement behind the curb. The concrete driveway aprons for the apartment building along Ashley Lane were also opened to full access.

Next Week (10/13–10/18):

Road crews will focus on completing punch list items and preparing the roadway for the final wear course paving.

Please note that all work is weather-dependent and subject to change

City Contact:

Please contact David Ray, Asst. City Engineer by email or call 651-450-2541.

More info at: www.ighmn.gov/pavement

* * * * * * *

If you no longer wish to receive these messages, you may manage your preferences and unsubscribe at any time by visiting: www.ighmn.gov/list.asp?mode=del.

Please note, we will not sell or give your email address to any organization without your explicit permission.

 

Plain text message

2025 IGH Pavement Management Initiative - 50th Street Area St (Babcock to TH 3)
Construction Update
This Week (10/06–10/11):
Restoration work took place this week, including sod placement behind the curb. The concrete driveway aprons for the apartment building along Ashley Lane were also opened to full access.

Next Week (10/13–10/18):
Road crews will focus on completing punch list items and preparing the roadway for the final wear course paving.

Please note that all work is weather-dependent and subject to change

City Contact:
Please contact David Ray, Asst. City Engineer by email or call 651-450-2541.

More info at: www.ighmn.gov/pavement

* * * * * * *

If you no longer wish to receive these messages, you may manage your preferences and unsubscribe at any time by visiting: www.ighmn.gov/list.asp?mode=del.

Please note, we will not sell or give your email address to any organization without your explicit permission.

SMS message

Sod and restoration work were completed this week. Next week, crews will finish punch list items and prep the road for final paving.