Construction Update: 50th Street Area (Babcock to TH 3)

Formatted HTML message

2025 IGH Pavement Management Initiative - 50th Street Area St (Babcock to TH 3)

Construction Update

This Week (09/15–09/20):

Utility crews have raised castings this past week while the concrete crew worked on curb along Ashley Lane. Additionally, the concrete crew worked on pouring new sidewalks along 50th Street. The road crew removed the excess road material from the road and began work to prepare the road for paving.

Next Week (09/22–09/27):

The road crew will be working to prepare the road early in the week and are planning to pave the road mid-week.

Please note that all work is weather-dependent and subject to change

City Contact:

Please contact David Ray, Asst. City Engineer by email or call 651-450-2541.

More info at: www.ighmn.gov/pavement

* * * * * * *

If you no longer wish to receive these messages, you may manage your preferences and unsubscribe at any time by visiting: www.ighmn.gov/list.asp?mode=del.

Please note, we will not sell or give your email address to any organization without your explicit permission.

 

Plain text message

2025 IGH Pavement Management Initiative - 50th Street Area St (Babcock to TH 3)
Construction Update
This Week (09/15–09/20):
Utility crews have raised castings this past week while the concrete crew worked on curb along Ashley Lane. Additionally, the concrete crew worked on pouring new sidewalks along 50th Street. The road crew removed the excess road material from the road and began work to prepare the road for paving.

Next Week (09/22–09/27):
The road crew will be working to prepare the road early in the week and are planning to pave the road mid-week.

Please note that all work is weather-dependent and subject to change

City Contact:
Please contact David Ray, Asst. City Engineer by email or call 651-450-2541.

More info at: www.ighmn.gov/pavement

* * * * * * *

If you no longer wish to receive these messages, you may manage your preferences and unsubscribe at any time by visiting: www.ighmn.gov/list.asp?mode=del.

Please note, we will not sell or give your email address to any organization without your explicit permission.

SMS message

This week: Curb work and preparation for paving on Ashley lane Next week: Additional paving preparation and paving mid-week.